Project Weekend 8/9 Nov 2003
Extension Work
< August 2003 (extension) | 22/23 November 2003 >
|
Whilst the 'bypass' is being built, another team makes progress with the Traeth Mawr run-round loop. Here, the topsoil is being scraped back, before the levelling fill is extended further. The loop will be temporary, existing only until Phase 2 takes the line to Pont Croesor. Therefore, this region may have further earthwork once the loop has been lifted, Mark Holden | |
|
858x643, 113KiB | |