Civil's Week July/August 2003
P-Way Work
< 2003 at Rhyd Ddu | August 2003 (No.9 Road) >
The Extension Work
At this stage of construction, the Extension consists of three activities: fencing to keep out livestock and delineate public footpaths; excavating and filling to get the level of the formation correct; laying and rolling the slate-waste haul road on which the railway will be laid.
Fencing Work
A major achievement in Civil's Week was the sheer amount of fencing completed. Because a public footpath runs alongside the railway here, there are three fences to construct. The outer stockproof fences (including repairs to existing dry stone walling) are done first, and the footpath fence is done concurrently with the other work.
|
At the end of Civil's Week, the 520m mark had been reached. About 170m had been done in 7 days. The work is continuing on later weekends and week-long sessions. If you've enjoyed these photographs and might like to lend a hand yourself, we are an all-volunteer workforce which welcomes enthusiastic new participants. Mark, driving the excavator here amd who you've seen in many of the other photos, is the volunteer coordinator. Please email Mark with your enquiry, however tentative. Andy Goodwin | |
|
640x480, 71KiB (large file: 1280x960, 228KiB ) | |