Civil's Week July/August 2003
P-Way Work
< 2003 at Rhyd Ddu | August 2003 (No.9 Road) >
The Extension Work
At this stage of construction, the Extension consists of three activities: fencing to keep out livestock and delineate public footpaths; excavating and filling to get the level of the formation correct; laying and rolling the slate-waste haul road on which the railway will be laid.
Fencing Work
A major achievement in Civil's Week was the sheer amount of fencing completed. Because a public footpath runs alongside the railway here, there are three fences to construct. The outer stockproof fences (including repairs to existing dry stone walling) are done first, and the footpath fence is done concurrently with the other work.
|
James rolls the slate into the hard road on which the railway will be built. Yes, there really is a telegraph pole in the midle of the railway. But not for long - once it's cables have been certified defunct, it'll find a new home (possibly with the help of a chainsaw!) Rick Beton | |
|
596x397, 55KiB (large file: 1192x795, 185KiB ) | |

