The Extension Work
At this stage of construction, the Extension consists of three activities: fencing to keep out livestock and delineate public footpaths; excavating and filling to get the level of the formation correct; laying and rolling the slate-waste haul road on which the railway will be laid.
Fencing Work
A major achievement in Civil's Week was the sheer amount of fencing completed. Because a public footpath runs alongside the railway here, there are three fences to construct. The outer stockproof fences (including repairs to existing dry stone walling) are done first, and the footpath fence is done concurrently with the other work.
|
Dave the Surveyor and Chief Civil Engineer is seen at the controls, taking a 'hands-on' approach. Quick and accurate levelling is quite a challenge for excavator drivers: Dave and Mark (seen by the dumper) are two of the most accomplished levellers in the gang. Rick Beton | |
|