Civil's Week 2002
P-Way Work
< Spring 2002 | Easter 2003 >
|
Progress looking north is looking good. Most of the left-hand point is done and the panel of plain line connecting to the 60lb right-hand point is being assembled. The left-hand spur will be a headshunt in the final layout, avoiding possibly dangerous conflicting moves between trains at Pen-y-Mount station and other trains running through to/from the FR Harbour Station. Rick Beton | |
|
398x599, 75KiB | |
For an alternative summary of recent works, see the On-line Journal.