Civil's Week 2002
P-Way Work
< Spring 2002 | Easter 2003 >
|
About half done, the straight components of the left-hand point are finished. Then in will go the right-hand gut rail, joining the crossing to the right-hand switch blade. This allows the left-hand curve to be gauged off, thus completing the point. But first, attention will turn to the short closure between the two points. The former headshunt under our feet on the right still has its crossing timbers, used for vehicle access to & from Gelert's Farm. I remember building it in 1992 (?) and we did too good a job! It took ages to disassemble! Dave Allan | |
|
393x498, 66KiB (large file: 595x754, 117KiB ) | |
For an alternative summary of recent works, see the On-line Journal.