Gwyrfai Valley Track Construction, June 2000
WHLR Project Phase 2
< July 2000 | December 2000 >
This is a selection of photos taken whilst assisting the construction of the W.H. Light Railway from Dinas towards Waunfawr (Phase 2).
| Click the thumbnails to see larger pictures | |
|
|
Groan! Waking up at six a.m. to see Nigel tucking into strawberries was a real treat! (Believe that, ...) Rick Beton 448x293, 30KiB (large file: 897x586, 107KiB ) |
|
|
After the usual induction, we joined the comfortably fitted-out transport at the work site, a mile or so east of Dinas. WRLRly Ltd Manager Roland Doyle was very helpgful in personally attending to arrangements. Rick Beton 448x294, 41KiB (large file: 897x589, 156KiB ) |
|
|
The view westwards towards Dinas shows a pair of ballast wagons blocking the (then incomplete) route downhill to Dinas. Rick Beton 452x294, 30KiB (large file: 904x589, 109KiB ) |
|
|
Looking back from the train, Tryfan Junction station looks like any other pile of stones, surrounded as it was at that stage by a materials depot. Rick Beton 448x293, 28KiB (large file: 897x586, 107KiB ) |
|
|
There was a walk from the train's limit of movement along the track that was, at that time, only partially complete. One particular type of track bolt was in short supply; the left hand rail wouldn't have been safe with the weight of the locomotive (the Funkey). Rick Beton 448x293, 51KiB (large file: 897x586, 210KiB ) |
|
|
Fine figures of men! ...or something! The missing bolts are clearly absent, seen in this photo. Rick Beton 448x291, 52KiB (large file: 897x583, 208KiB ) |
|
|
Here, in the beautiful Gwyrfai valley, there are three thresholds: the end of the rails, where the WHLRly Ltd paid gangers are hard at work; the extent of the laid-out sleepers, where our gang was to work; and a mile nearer Waunfawr (behind the camera), the end of the completed base layer of ballast. Rick Beton 300x443, 47KiB (large file: 600x886, 174KiB ) |
|
|
It's quite easy really: use the marked-up rope to show where to put the sleepers. We worked in pairs to keep our strength up. Actually, anyone strong and healthy can easily lift one of these sleepers by oneself, but there was no need to wear ourselves out in the first few hours. Rick Beton 448x293, 52KiB (large file: 897x586, 209KiB ) |
|
|
Ten minutes for a well-earned break. Rick Beton 450x293, 52KiB (large file: 900x586, 194KiB ) |
|
|
The sleepers were delivered in packs. One of the main advantages of these steel sleepers is that they are compact during transit. The packs are held together using steel bands that had to be sawn off with a hacksaw, as demonstrated by Andy and Nick. Rick Beton 448x293, 48KiB (large file: 897x586, 191KiB ) |
|
|
An hour or two later, the march of the sleepers stopped. We'd reached a small excavator and the end of the first stage ballast. Rick Beton 450x293, 52KiB (large file: 900x586, 192KiB ) |
|
|
We encountered some unusual variety in some of the batches of sleepers. ;-) Rick Beton 301x444, 56KiB (large file: 603x889, 215KiB ) |
|
|
We caught the train back past the depot where we'd started out, and on to the western head of steel. Then we'd walked the rest of the way into Dinas. Here, some large engineering works had been completed on the embankment and unusual bridge which formerly had had the stream running underneath. Anyone visiting this spot now will be amazed to see how the vegetation has reclaimed this area, back to its familiar verdance. Rick Beton 450x293, 46KiB (large file: 900x586, 164KiB ) |
|
|
Our second day was spent laying track. Actually, this is remarkably tricky on the tight curves where we were working, and we soon had admiration for the regulars who averaged four or five panels a day. The photo shows the rollers on the sleepers along which the rails are slid to get them from the Rail Mover trucks into their positions. Bearing in mind that the rails each weigh over half a tonne, you'll appreciate this takes not only strength but also care! Rick Beton 448x291, 51KiB (large file: 897x583, 209KiB ) |
|
|
The Rail Mover trucks are well-suited to the job. Both rails are carried along slung under the trucks, with the lifting arms fastened in the raised position. Rick Beton 448x293, 44KiB (large file: 897x586, 176KiB ) |
|
|
A side view of a Rail Mover shows the simple but elegant system. Rick Beton 450x294, 41KiB (large file: 900x589, 152KiB ) |
|
|
Once the rails are in the right place on the sleepers, the fastening up begins. This has to work along from the fishplated end because of the curvature. So it's inherently not a fast process! Rick Beton 448x293, 44KiB (large file: 897x586, 170KiB ) |
|
|
Of course, curvature means that the inner rail has to be shortened and re-drilled. Andy is showing how to make fireworks with a disccutter. Rick Beton 300x443, 50KiB (large file: 600x886, 177KiB ) |
|
|
'Steamhammer' Jones has clearly run out of steam! Rick Beton 450x294, 52KiB (large file: 900x589, 199KiB ) |
|
|
Once the track is assembled, careful measurement by the foreman and brute force by the gang ensures that the alignment is spot on. Rick Beton 300x444, 48KiB (large file: 600x889, 187KiB ) |
|
|
Here is our day's work: three and a half panels around a bend. Some blokes had to leave at that time. We hadn't even come close to our record breaking 12 panel day of three years earlier, but that day had had three times more people and was in a straight line. It's surprising what difference the curves make. Isn't it a beautiful place?! Rick Beton 300x443, 55KiB (large file: 600x886, 205KiB ) |
For an alternative summary of recent works, see the On-line Journal.
See also
- More Scenes of the Present Day
- Scenes of the Old Welsh Highland Railway
- More about the Welsh Highland Railway Ltd
* Civil's Week Reports in The Journal:

