Click here for the
Latest News
- 1863
-
The Croesor Tramway was built to carry goods between the Croesor
Valley and Portmadoc.
More history
.
- 1872
-
The North Wales Narrow Gauge Railways Company was incorporated
by Act of Parliament.
More history
.
- 1877
-
The North Wales Narrow Gauge Railways commenced operating
between Dinas and Rhyd Ddu.
- 1901
-
The Portmadoc, Beddgelert and South Snowdon Railway Co. was
incorporated under an Act of Parliament. Some time later, it
started but never finished construction of the link from Rhyd
Ddu to Portmadoc.
More history
.
- 1922
-
The Welsh Highland Railway (Light Railway) Company was formed.
Construction was completed a year later.
More history
.
- 1927
-
The Welsh Highland Railway Co. went broke but continued
operating under the control of the Receiver.
More history
.
- 1934
-
The Ffestiniog Railway leased the Welsh Highland Railway and
took over its operation.
More history
.
- 1937
-
The WHR finally ceased operating, although passenger services
had its operation.
More history
.
- 1940
-
From 1940 onwards, the rails & equipment were removed for
the War effort.
More history
.
- 1941
-
The first attempt to re-vitalise the WHR was made.
- 1944
-
A High Court winding up order was issued for the defunct Welsh
Highland Railway (Light Railway) Co in 1944 (this order has
still to be completed).
- 1961
-
The Welsh Highland Society was formed. In 1964 it became the
Welsh Highland Light Railway (1964) Co Ltd (often called "
The '64 Co
") (Later, the name changed to the Welsh Highland Railway Ltd).
- 1980
-
The railway opened from Porthmadog to Pen-y-Mount (3/4 mile) and
plans were made over the next few years for Gwynedd County
Council (GCC) to acquire old trackbed from the Official Receiver
of the old company & lease sections back to the WHR'64 Co (
background
). This WHR/Council partnership developed over the next fourteen
years.
- 1983
-
The decision to bid for the trackbed in partnership with GCC was
adopted formally by the WHR'64 Co. (
background
). A rival approach of gathering the assets of the 1922 Company
and resurrecting it resulted in the formation of a separate
organisation (Trackbed Consolidated Limited). Both approaches
subsequently failed, but for quite different reasons.
- 1987
-
The Ffestioniog Railway (F.R.) secretly offered to buy the
trackbed and give it to the County Council on condition that it
would never be used for railway purposes. This
came into the open
in 1990.
- 1988
-
Restoration of Hunslet 2-6-2T
Russell
was completed.
- 1991
-
The F.R. attempted to gain control of the trackbed by applying
to the High Court in London to bring the 1922 Company back out
of receivership. This attempt failed: it was ruled 'Wholly
Misconceived' by the High Court Judge (
here is the reason
why this had not been attempted before).
- 1992
-
The F.R. attempted to gain control of the trackbed by applying
for a 'Light Railway Transfer Order'.
-
Restoration of Bagnall 0-4-2T
Gelert
was completed.
- 1993
-
The F.R. launched its own 'Welsh Highland Railway Society'
(nothing to do with the existing WHR'64 Co nor the earlier 1961
Society of that name).
- November 1993
-
A 4 week long Public Inquiry was held in Caernarfon in 1993 to
recommend which party should be allowed to purchase the 1922
company assets and liabilities. The recommendation was clear and
was strongly in favour of the joint WHR/Council application.
- July 1994
-
On the same day as he resigned from office, the Minister of
Transport overturned the result of the Public Inquiry. Instead,
the application by the F.R. was upheld.
-
This decision attracted widespread criticism in the press. The
W.H.R. Ltd considered challenging the basis on which the
decision had been reached, but was unable to call it into
question because of the high cost of High Court litigation
(W.H.R. Ltd is a registered charity with only limited
resources.) A period of bitter animosity with the F.R. followed.
- August 1995
-
In order to further the overall objectives of rebuilding the
railway and to foster goodwill between the two parties, the
WHR'64 Co withdrew its opposition to the F.R.'s Caernarfon-Dinas
LRO, and vigorously encouraged GCC to do the same. Strong
support was given to the Planning Permission request by the F.R.
for this section.
-
Further impetus was given by the WHR'64 Co
offering to rebuild to Pont Croesor
at its own cost and handing over the completed section to the
F.R.. This offer has since been accepted by the F.R., and is not
limited just to reaching Pont Croesor.
-
(
Here's
more on joining in
—
and
—
some pix of trackbuilding in action
.
)
- October 1995
-
rebuilding of the WHR. This represents almost half of the
estimated cost of a rebuilt railway as far as Rhyd-Ddu by the
end of the century. Full payment of the grant is dependent on
this being done. The award has to be matched pound-for-pound by
additional finance or equivalent volunteer labour.
-
The Welsh Highland Railway Experience at Porthmadog was
announced (see the
Press Release
).
- December 1995
-
Planning Permission was granted for the building and operation
of the Caernarfon-Dinas section.
- January 1996
-
A
Memorandum of Understanding
was drafted between the WHR'64 Co and the F.R. This opened the
potential for an effective phase of cooperation between the two
parties. It was fully ratified by the WHR'64 Co.
- April 1996
-
The
Memorandum of Understanding
was angrily rejected by the F.R. board. This followed the sudden
departure of F.R. General Manager Gordon Rushton.
- May 1996
-
The Welsh Highland Light Railway (1964) Co. Ltd. formally became
known as the Welsh Highland Railway Ltd.
- July 1996
-
As a gesture of new cooperation, The WHR P-Way gang built a
siding for the F.R. at Glan-y-Pwll (
pictures
). A
Joint Press Release
describes this and the warming relationship between the F.R. and
WHR. No volunteer effort was available from the Welsh Highland
Railway Society.
-
Gwynedd County Council withdrew its opposition to the F.R.'s
Caernarfon-Dinas LRO, as the WHR'64 Co had done in August 1995.
- September 1996
-
Porthmadog Town Council resolved to oppose the construction of a
rail link across the town. The F.R. plan was to link the
existing WHR at Pen-y-Mount across the standard gauge tracks to
a new terminus at Llyn Bach, right next to the supermarket. A
connecting line would run across Brittania Bridge to the Harbour
Station. At the Public Inquiry, eleven 'Material Objections' to
the cross-town link had been raised, making this half-mile the
hardest and most expensive section to rebuild.
-
The first consignment of rail (700 tons) was delivered to Dinas
yard, together with several wagons, all imported from South
Africa.
- October 1996
-
The European Regional Development Fund announced a grant of
£735,600 towards the Caernarfon to Dinas railway. This is
effectively doubled up pound-for-pound by part of the Millenium
Commission award (announced
October 1995
).
-
The Wales Tourist Board announced a grant of
£100,000 towards the cost of importing two NGG16 Beyer Garratt
locomotives from South Africa and the procurement of some
carriages.
- November 1996
-
At the latest board meeting, the WHR Ltd decided to lift the
current membership suspensions from the 5 Trackbed Consolidated
Ltd members (Messrs Ewing, Lodge, & 3 Prestons).
These members had been suspended since 1983 (
background
). As a gesture of reconciliation, it was felt that this was
long enough.
- December 1996
-
The contract to clear, ballast and fence the formation between
Caernarfon and Dinas was let to Mowlem.
- January 1997
-
Gwynedd County Council temporarily closed the Lon Eifion
cycleway along the Caernarfon - Dinas trackbed. This was to
allow access for the contractors. The cycleway was reinstated in
the summer alongside the newly fenced-off railway.
-
Construction of the Caernarfon - Dinas section commenced at
Dinas. The contractors cleared the trackbed and provided
fencing, drainage and first-level ballast. The tracklaying was
to be done by volunteers.
- May 1997
-
0-4-0
Sezela No. 4
restoration had proceeded to the point where the locomotive can
operate under its own steam.
-
Tracklaying started in Dinas Llanwnda, heading northwards
towards Caernarfon.
-
This had come twenty years after the start of the WHR
reconstruction in Porthmadog, a hiatus resulting from legal and
bureaucratic obstacles and somewhat prolonged by rivalry between
different organisations, as outlined above.
- June 1997
-
The New Labour Minister for Transport, announced a Public
Inquiry into the reconstruction of the Welsh Highland Railway.
- July 1997
-
The F.R. application for Transport and Works Act powers were set
back six weeks whilst notices are served allowing further
objections to alterations to footpaths and bridleways affected
by the railway (see the House of Commons
Written Answers"
reply in Hansard).
-
The annual Civil's Week trackbuilding included
laying a significant stretch of track
(260 yd) towards Caernarfon by the W.H.R. Ltd gang, in
collaboration with W.H.R.S. volunteers and W.H. Light Rly Ltd
employees.
-
Restoration of the 1891
'Gladstone'
coach
was completed.
- August 1997
-
Following the significant contribution to track laying (see
above), more concrete proposals entered discussions and
negotiations between the W.H.R. Ltd and F.R..
-
Track construction towards Caernarfon entered the outskirts of
that town. The railhead was at Pont Seiont and 3 sets of points
were delivered to Caernarfon. Work started on extending the long
shed in the ex-Welsh Water yard for locomotive use.
- September 1997
-
Discussions between the F.R. and W.H.R. led to
seven heads of agreement
. An Extraordinary General Meeting was held for W.H.R. members
to debate this (see
background article
).
- October 1997
-
The F.R. withdrew its earlier agreement to a draft contract with
the W.H.R., insisting instead on almost complete handover of
rights and assets owned by the W.H.R. This was a serious
backward step which was difficult to understand.
-
The F.R. operated public train services between Dinas and
Caernarfon for a period of a few weeks.
- November 1997
-
Negotiations between the W.H.R. and F.R. continued. The earlier
reversal was overcome. A second
Memorandum of Understanding
was agreed (the first MoU
had earlier been rejected
).
- December 1997
-
The F.R. Public Inquiry (regarding the application for a
Transport and Works Order) started.
- January 1998
-
The F.R. Public Inquiry (regarding the application for a
Transport and Works Order) concluded.
-
Negotiations between the W.H.R. and F.R. reached a
Formal Agreement
, broadly similar to the draft agreement of August '97. This has
now been formally concluded.
- March 1998
-
Restoration work began on the ex-NWNGR buildings at Dinas.
- April 1998
-
Phase two of the Porthmadog Station building was completed (see
Journal 125
).
- October 1998
-
Co-operation between the WHR Ltd and F.R. improved following the
agreement earlier in the year. The F.R. donated the chassis of a
heritage coach
to the WHR and loaned some original slate wagons for
restoration. Also, several important items of heritage rolling
stock in full working order were lent for the "Dirty Chappies 5"
enthusiasts weekend.
- March 1999
-
The Snowdon National Park Authority Public Inquiry report was
issued with the recommendation that the WHR route be protected
for railway use. This policy had earlier been present in the
Eryri Local Plan, but the relevant clause had been deleted in
1998. The SNPA accepted the recommendation and reinstated the
relevant clause, thereby returning to their prior policy of
supporting the WHR.
- April 1999
-
The
Public Inquiry
report was issued with the recommendation by the Inspector that
the WHR should not be rebuilt. However, Deputy Prime Minister
John Prescott conditionally approved the reconstruction of the
entire WHR, subject to rockfall prevention plans being
satisfactory to the DETR. The F.R., to whom John Prescott is
'minded' to grant powers under the Transport and Works Act, have
appointed consultant surveyors to resolve the rockface
questions.
-
See the
Press Release
.
- June 1999
-
Deputy Prime Minister, John Prescott, approved the proposal to
rebuild the former Welsh Highland Railway through the Snowdonia
National Park.
-
"After giving very careful consideration to this complex and
sensitive case, I am satisfied that the benefits of the scheme
outweigh the disadvantages and that it would be in the public
interest to allow it to proceed.
-
"I said in April that I was inclined to grant the powers which
the Festiniog Railway Company needed to reconstruct the
railway. But before reaching a final decision, I wanted the
Company to undertake a detailed survey of the rock faces in
the vicinity of the Aberglastyn tunnels.
-
"A survey has since been completed by Ove Arup and Partners. I
have carefully considered their report, together with a review
of that report carried out by Hyder on behalf of the Snowdonia
National Park Authority, as well as other representations and
advice received. I am satisfied from this information that the
railway can safely be taken through the National Park without
causing unacceptable harm to the environment."
- July 1999
-
Statutory Instrument 1999 No. 2129
came into effect. This grants powers to the Festiniog Railway to
build and operate a railway along the course of the old Welsh
Highland Railway.
-
The National Farmers Union applied for a Judicial Review of the
granting of these powers, seeking to revoke the Order.
- November 1999
-
The F.R. issued Compulsory Purchase notifications to some
landowners at the northern end of the WHR trackbed. The
Compulsory Purchase comes into effect in February 2000.
Note that there remain considerable lengths of disputed land
on the trackbed, contrary to what was earlier reported on this
page.
-
The Judicial Review launched by the N.F.U. upheld the Secretary
of State's decision to grant the Transport and Works Order, by
which the Welsh Highland Railway is being rebuilt.
- April 2000
-
Tracklaying commenced on the eastward extension from Dinas to
Waenfawr (Welsh Highland Railway Caernarfon).
- July 2000
-
Tracklaying was completed between Dinas and Waunfawr (Welsh
Highland Railway Caernarfon).
- August 2000
-
Twenty years to the day after services began on the Welsh
Highland Railway (Porthmadog), some trackbed clearance took
place north of Porthmadog to facilitate surveying.
-
Train services started on the extended Welsh Highland Railway
(Caernarfon).
- September 2000
-
Over the weekend of the 16th - 17th September 2000, the
re-opening ceremony for the Dinas-Waunfawr extension involved
crews from both the Ffestiniog Railway and the Welsh Highland
Railway (Porthmadog), from whence
Russell
came to visit Dinas.
more
- End of 2000
-
Construction and tracklaying commenced southwards from Waunfawr.
- February 2001
- Trackbed clearance commenced northwards from Pen-y-Mount.
-
Foot & Mouth Disease halted both northward and southward
construction projects. Southward work recommenced gradually as
new disease control measures were introduced and restrictions
were gradually eased.
- June 2001
-
Track construction was completed as far as Betws Garmon station.
Tracklaying has since been progressing over the Rhyd-ddu to
Glanrafon section.
- August 2001
-
Trackbed clearance re-commenced northwards from Pen-y-Mount,
following the FMD hiatus and end of the bird-nesting season.
- August 2002
-
The preliminary junction north of Pen-y-Mount was installed,
consisting at this stage of two points.
more
- January 2003
-
Tracklaying started at Rhyd Ddu Station on the section northward
from there toward Waunfawr.
- March 2003
-
Planning permission was granted for the Pen-y-Mount to Traeth
Mawr extension, subject to certain caveats (
press release
). The northward extension started in earnest with fencing and
the construction of a haul road (the base on which the ballast
will be laid).
- July 2003
-
The FR's application for
£7.24M to fund Phases 4 and 5 (Rhyd Ddu to Porthmadog) was
rejected.
-
Extension Phase 3 from Waunfawr to Rhyd Ddu was formally opened
by HRH Prince Charles on 30th July, although passengers weren't
carried for three more weeks.
- August 2003
-
Extension Phase 3 from Waunfawr to Rhyd Ddu commenced operation
in mid August. The Caernarfon line now reaches 12 miles into
Snowdonia.
- February 2004
-
Phase I of the Pont Croesor Extension (northward from
Pen-y-Mount to Traeth Mawr) completed the fencing and formation
works.
- June 2004
-
Baldwin 4-6-0PT '794' arrived at Gelert's Farm for restoration
as '590'.
more
- September 2004
-
Project Rheilffordd Eryri - Phase 4 has been secured, with the
help of
£5m grant funding from the Welsh Assembly and the EU, plus a
similar amount of private funding, much of which is still to be
raised.
more
- September 2006
-
Formation of the Welsh Highland Railways Association
representing The Welsh Highland Railway Ltd, The Welsh Highland
Railway Society and The Welsh Highland Railway Heritage Group.
more
- November 2006
-
The new crossing on the level of the Cambrian Coast railway was
installed and marked the first visible construction of the
Porthmadog cross-town link. This is the only place in Britain
where a 2' gauge railway crosses standard gauge.
- - Latest News -
- March 2007
-
The Traeth Mawr extension opened. The line northward from
Pen-y-Mount was thus extended by about 1km to a point half way
to Pont Croesor.
See also:
-
Southward Construction:
-
Peter Johnson's Pages
sometimes include reports as published in
Steam Railway
and elsewhere.